Missouri Creek Stream Restoration

Project Overview

The 2021 study by Matrix Design Group identified the Missouri Creek sub-basin as one of the most at-risk areas in the Upper Clear Creek Watershed. The Missouri Creek sub-basin is in Gilpin County, upstream of North Clear Creek, Gilpin County High School, and the Missouri Lakes neighborhood. However, although the Matrix pre-wildfire planning study identified stream projects for larger streams and reaches, it did not evaluate smaller reaches like Missouri Creek, which runs along Missouri Gulch Road. Through the 2022 Senior Design Challenge program, Colorado School of Mines students are conducting preliminary field assessments, water quality and field data collection, and GIS analyses to recommend preliminary restoration designs in the Missouri Creek sub-basin.

Although the pre-wildfire planning study did not identify stream channel and floodplain projects for smaller reaches, two Forest Management projects (FM-34 & FM-35) were identified in the Missouri Creek sub-basin. These projects are part of the US Forest Service Yankee Hill Fuels Reduction project area, and must be carried out in partnership with the USFS. The CCWFHP is working on larger-scale collaborations with the USFS to accomplish forest management needs throughout the watershed and adjacent watersheds. Stream channel and floodplain projects will reduce impacts of post-fire runoff if a fire were to occur in the Missouri Creek sub-basin.

Mitigation Measures Proposed

CCWFHP plans to conduct a Request for Proposal process for final engineering designs for Missouri Creek stream restoration work, based on CSM 2022 Senior Design findings, including:

  1. Dredge the pooling pond and mine waste piles between pond and stream.

  2. Lateral stream movement to make the stream more sinuous.

  3. Replace outlet culverts near the Pickle Gulch Campground.

  4. Perform fuels reduction measures at the site.

Estimated Costs & Permitting

Costs and permitting needs are to be determined in the Request for Proposals process in Phase 2 (slated for 2023).

Phase 1: CSM Senior Design

Through the 2022 Senior Design Challenge program, Colorado School of Mines students are conducting preliminary field assessments, water quality and field data collection, and designing a stream channel restoration project on Missouri Creek, a tributary to North Clear Creek. The CSM Senior Design student team was asked to identify stream restoration and floodplain preservation locations on Missouri Creek using the same methods applied by Matrix: relative elevation models (REMs) and aerial imagery. The students also met with stakeholders about the project, including Blackhawk City Council meetings and the Upper Clear Creek Watershed Association.

Timeline: CSM students began work in Spring 2022, with an initial site visit in April 2022, and additional flow, water quality, and soil sampling in July, September, and October 2022,.

In December 2022, the CSM team provided 30% project design & restoration recommendation to the Partnership at the conclusion of their Senior Design project.

Mitigation Measures Proposed

CCWFHP plans to conduct a Request for Proposal process for final engineering designs for Missouri Creek stream restoration work based on CSM 2022 Senior Design findings, including:

  1. Dredge the pooling pond and mine waste piles between pond and stream.

  2. Lateral stream movement to make the stream more sinuous.

  3. Replace outlet culverts near the Pickle Gulch Campground.

  4. Perform fuels reduction measures at the site.

Birds-eye view diagram of proposed mitigation measures at Missouri Creek site — Figure 9 from the 2022 CSM Senior Design report.

Phase 2: Outreach & Full Design

In June 2022, the CWCB Healthy Rivers Fund grant program awarded $20,000 to support 1) final design engineering, 2) permitting, and 3) public outreach to facilitate implementation.

Timeline: The HRF funds were contracted in Fall 2022 and will be used in 2023 to conduct outreach on project design recommendations, and to contract an engineering-design firm following an RFP based on the CSM students’ design work.

Phase 3: Project Implementation

During Phase 2, the CCWFHP will begin coordinating implementation grant funds and matching dollars to support timely project implementation upon completion of the design and permitting process. More information to come on this step as Phase 2 progresses.